Construction Timeline

Stratford Plan · Lot 47, Ashlyn Creek

Done

4

Total

14

Close

Aug 27

  1. Silt Fence & Site Prep

    Complete
    Feb 9 – Feb 14, 2026
    100%

    Erosion control approved

  2. Lot Clear & Excavation

    Complete
    Feb 16 – Feb 23, 2026
    100%
  3. Footings & Foundation

    Complete
    Feb 24 – Mar 13, 2026
    100%

    Slab inspection passed Mar 13

  4. Plumbing Rough-In

    Complete
    Mar 16 – Mar 27, 2026
    100%
  5. Framing

    In Progress← We are here
    Mar 30 – May 16, 2026
    45%

    Currently building 2nd-floor walls

  6. Roofing & Dry-In

    Upcoming
    May 19 – May 29, 2026

    Inspection scheduled May 28

  7. HVAC, Electrical & Plumbing Trim

    Upcoming
    Jun 1 – Jun 19, 2026
  8. Insulation

    Upcoming
    Jun 22 – Jun 26, 2026

    Inspection scheduled Jun 26

  9. Drywall

    Upcoming
    Jun 29 – Jul 17, 2026
  10. Trim, Cabinets & Paint

    Upcoming
    Jul 20 – Aug 7, 2026
  11. Flooring & Tile

    Upcoming
    Aug 10 – Aug 17, 2026
  12. Fixtures & Final Mechanicals

    Upcoming
    Aug 18 – Aug 21, 2026

    Final inspection Aug 24

  13. Punch List & Walk-Through

    Upcoming
    Aug 25 – Aug 26, 2026
  14. Close

    Upcoming
    Aug 27, 2026

    Closing target