Construction Timeline
Stratford Plan · Lot 47, Ashlyn Creek
Done
4
Total
14
Close
Aug 27
- Feb 9 – Feb 14, 2026
Silt Fence & Site Prep
Complete100%Erosion control approved
- Feb 16 – Feb 23, 2026
Lot Clear & Excavation
Complete100% - Feb 24 – Mar 13, 2026
Footings & Foundation
Complete100%Slab inspection passed Mar 13
- Mar 16 – Mar 27, 2026
Plumbing Rough-In
Complete100% - Mar 30 – May 16, 2026
Framing
In Progress← We are here45%Currently building 2nd-floor walls
- May 19 – May 29, 2026
Roofing & Dry-In
UpcomingInspection scheduled May 28
- Jun 1 – Jun 19, 2026
HVAC, Electrical & Plumbing Trim
Upcoming - Jun 22 – Jun 26, 2026
Insulation
UpcomingInspection scheduled Jun 26
- Jun 29 – Jul 17, 2026
Drywall
Upcoming - Jul 20 – Aug 7, 2026
Trim, Cabinets & Paint
Upcoming - Aug 10 – Aug 17, 2026
Flooring & Tile
Upcoming - Aug 18 – Aug 21, 2026
Fixtures & Final Mechanicals
UpcomingFinal inspection Aug 24
- Aug 25 – Aug 26, 2026
Punch List & Walk-Through
Upcoming - Aug 27, 2026
Close
UpcomingClosing target