Niblock Purchasing
Procurement Pipeline
12 items · $108,500 estimated value
AI Procurement Alert
3 items need quotes this week. Windows for Lot 63 have a 6-week lead time — order by May 8 to stay on schedule. Countertops for Lot 55 quoted but needs approval before lead time expires.
Needs Quote
3
$28.2K est.
Quoted
3
$22.7K est.
PO Created
3
$30.9K est.
Ordered
3
$26.6K est.
12 Items
$108,500 estimated| ID | Item | Job | Vendor | Estimate | Lead Time | Due | Priority | Stage |
|---|---|---|---|---|---|---|---|---|
| PRO-101 | Windows – Lot 63 Cypress | Lot 63 – Cypress | TBD | $14,200 | 6 weeks | May 8 | urgent | Needs Quote |
| PRO-102 | Cabinets – Lot 47 Hawthorne | Lot 47 – Hawthorne | TBD | $9,800 | 4 weeks | May 12 | normal | Needs Quote |
| PRO-103 | Garage Doors – Lot 61 Oakmont | Lot 61 – Oakmont | TBD | $4,200 | 3 weeks | May 15 | normal | Needs Quote |
| PRO-104 | Flooring – Lot 52 Magnolia | Lot 52 – Magnolia | Shaw Direct | $7,600 | 2 weeks | May 5 | normal | Quoted |
| PRO-105 | Appliances – Lot 38 Cedar | Lot 38 – Cedar | Ferguson | $8,900 | 3 weeks | May 10 | normal | Quoted |
| PRO-106 | Countertops – Lot 55 Willow | Lot 55 – Willow | Stone Works | $6,200 | 4 weeks | May 6 | urgent | Quoted |
| PRO-107 | Lumber – Lot 55 Willow | Lot 55 – Willow | Carolina Lumber | $18,400 | 1 week | May 3 | normal | PO Created |
| PRO-108 | Electrical – Lot 61 Oakmont | Lot 61 – Oakmont | SE Electrical | $8,200 | 1 week | May 6 | normal | PO Created |
| PRO-109 | Drywall – Lot 33 Maple | Lot 33 – Maple | Metro Drywall | $4,350 | 3 days | May 8 | normal | PO Created |
| PRO-110 | HVAC Units – Lot 47 Hawthorne | Lot 47 – Hawthorne | Blue Ridge HVAC | $12,300 | Shipped | May 1 | normal | Ordered |
| PRO-111 | Roofing – Lot 29 Birchwood | Lot 29 – Birchwood | Reliable Roofing | $7,600 | Delivered | Apr 30 | normal | Ordered |
| PRO-112 | Plumbing – Lot 38 Cedar | Lot 38 – Cedar | Piedmont Plumbing | $6,750 | In transit | May 2 | normal | Ordered |