Niblock Purchasing
Receiving
10 deliveries · $103,490 total value
AI Delivery Forecast
2 deliveries in transit today — concrete for Lot 55 (8 AM, ensure pump truck scheduled) and plumbing for Lot 38 (ETA 2 PM). Anderson Windows on 3-week lead, track closely.
Total Value
$103K
Scheduled
4
In Transit
2
$16,550
Delivered
4
10 Deliveries
$103,490 total| PO # | Vendor | Job | Items | Qty | Value | Expected | Received By | Status |
|---|---|---|---|---|---|---|---|---|
| PO-2026-0412 | Carolina Lumber Co | Lot 47 – Hawthorne | Framing lumber package | 142 pcs | $18,450 | May 5 | — | scheduled |
| PO-2026-0410 | Piedmont Plumbing | Lot 38 – Cedar | Rough-in plumbing kit | 1 kit | $6,750 | May 2 | — | in-transit |
| PO-2026-0409 | Blue Ridge HVAC | Lot 61 – Oakmont | 3-ton heat pump + air handler | 2 units | $12,300 | Apr 30 | Mike Torres | delivered |
| PO-2026-0408 | Concrete Solutions | Lot 55 – Willow | Foundation concrete (18 yards) | 18 CY | $9,800 | May 1 | — | in-transit |
| PO-2026-0407 | Reliable Roofing | Lot 29 – Birchwood | Architectural shingles (42 sq) | 42 sq | $7,600 | Apr 28 | Jason Wright | delivered |
| PO-2026-0405 | ProPaint Supply | Lot 38 – Cedar | Interior paint package | 28 gal | $3,200 | May 10 | — | scheduled |
| PO-2026-0404 | Carolina Lumber Co | Lot 55 – Willow | Framing lumber - 2nd floor | 186 pcs | $22,100 | May 3 | — | scheduled |
| PO-2026-0403 | Anderson Windows | Lot 61 – Oakmont | Vinyl DH windows (18 units) | 18 EA | $14,800 | May 15 | — | scheduled |
| PO-2026-0402 | Home Depot Pro | Lot 52 – Magnolia | Hardware & fasteners assortment | 4 boxes | $2,890 | Apr 22 | Sarah Chen | delivered |
| PO-2026-0401 | SE Electrical | Lot 38 – Cedar | Panel + breakers + wire | 1 lot | $5,600 | Apr 24 | Thomas Niblock | delivered |