Change Order Impact Analysis
$1.4M
Net Cost Impact
67 days
Total Schedule Impact
$4,200
Avg CO Cost
78%
Approval Rate
Subdivision Impact Summary
| Subdivision | CO Count | Total Amount | Schedule Days | Avg Cost |
|---|---|---|---|---|
| Magnolia Ridge | 14 | $187,500 | 11d | $13,393 |
| Heritage Oaks | 12 | $156,200 | 9d | $13,017 |
| Stonebridge | 11 | $142,800 | 10d | $12,982 |
| Willow Creek | 10 | $198,400 | 14d | $19,840 |
| Peachtree Townhomes | 13 | $134,600 | 8d | $10,354 |
| Cedar Bluff | 9 | $112,300 | 5d | $12,478 |
| Brookfield Manor | 11 | $268,200 | 6d | $24,382 |
| Ashlyn Creek | 9 | $200,000 | 4d | $22,222 |
COs by Category
Owner Request34 (38%)
38%
Field Condition22 (25%)
25%
Design Error15 (17%)
17%
Code Requirement10 (11%)
11%
Allowance Overage8 (9%)
9%
Top 5 Largest Change Orders
1
CO-1044$15,600
Foundation redesign due to soil report — WC-118
2
CO-1052$13,500
Sewer line reroute - utility conflict — WC-122
3
CO-1043$12,300
Add covered patio extension — SB-305
4
CO-1049$11,400
Retaining wall extension — MR-115
5
CO-1047$9,200
Storm drain reroute — BM-203