Schedule
Construction timeline by job
On schedule Behind OverdueMay 1, 2026
Task / Subcontractor
Start
Days
Lot 47 – Hawthorne
Framing
Carolina Lumber
Apr 20
12d
Rough Plumbing
Piedmont Plumbing
May 4
8d
Rough Electrical
SE Electrical
May 6
7d
HVAC Rough
Blue Ridge HVAC
May 11
6d
Insulation
Carolina Lumber
May 18
4d
Drywall
Metro Drywall
May 22
10d
Lot 55 – Willow
Foundation
Carolina Lumber
Apr 13
10d
Framing
Carolina Lumber
Apr 27
14d
Windows
Carolina Lumber
May 15
5d
Roofing
Reliable Roofing
May 20
6d
Rough Plumbing
Piedmont Plumbing
May 25
8d
Rough Electrical
SE Electrical
May 27
7d
Lot 61 – Oakmont
Paint
Bernardo's Painting
Apr 22
10d
Cabinets
Carolina Lumber
May 4
6d
Countertops
Carolina Lumber
May 8
3d
Trim
Carolina Lumber
May 11
5d
Final Electrical
SE Electrical
May 15
4d
Final Plumbing
Piedmont Plumbing
May 18
3d
Apr 13
Week 1
Apr 20
Week 2
Apr 27
Week 3
May 4
Week 4
May 11
Week 5
May 18
Week 6
May 25
Week 7
Jun 1
Week 8
Jun 8
Week 9
Jun 15
Week 10
Jun 22
Week 11
Jun 29
Week 12
TODAY
Carolina Lumber100%
Piedmont Plumbing25%
SE Electrical15%
Blue Ridge HVAC0%
Carolina Lumber0%
Metro Drywall0%
Carolina Lumber100%
Carolina Lumber35%
Carolina Lumber0%
Reliable Roofing0%
Piedmont Plumbing0%
SE Electrical0%
Bernardo's Painting55%
Carolina Lumber50%
Carolina Lumber30%
Carolina Lumber10%
SE Electrical0%
Piedmont Plumbing0%