Takeoffs
Estimating

Material Takeoffs

Active material takeoff projects with quantity counts and category breakdowns.

Beckett Ridge — Lot 14
Plan: Beckett · 1,842 items counted
Total Materials
$198,400
100%
Lumber$62,400
Concrete$24,800
Roofing$21,300
Siding$18,900
Windows/Doors$42,600
Hardware$28,400
Cypress Hollow — Lot 7
Plan: Morgan (Custom) · 1,156 items counted
Total Materials
$142,800
72%
Lumber$48,200
Concrete$19,400
Roofing$15,800
Siding$14,200
Windows/Doors$26,400
Hardware$18,800
Sweetwater Ridge — Lot 22
Plan: Arlington · 1,448 items counted
Total Materials
$168,200
88%
Lumber$54,100
Concrete$21,200
Roofing$17,900
Siding$16,400
Windows/Doors$34,800
Hardware$23,800
Cypress Hollow — Lot 11
Plan: Stratford · 1,312 items counted
Total Materials
$154,800
100%
Lumber$48,800
Concrete$19,200
Roofing$16,400
Siding$14,600
Windows/Doors$32,400
Hardware$23,400
Highland Park — Lot 3
Plan: Aspen · 622 items counted
Total Materials
$89,400
42%
Lumber$32,600
Concrete$14,200
Roofing$12,800
Siding$9,800
Windows/Doors$12,400
Hardware$7,600