Change Order Log
12
Pending
8
In Review
67
Approved
2
Rejected
| CO# | Description | Job/Lot | By | Category | Amount | Days | Status | Date |
|---|---|---|---|---|---|---|---|---|
| CO-1041 | Upgraded kitchen countertops | MR-112 | Homeowner | Owner Request | $4,200 | 3d | Approved | 2026-04-28 |
| CO-1042 | Relocate HVAC ductwork | HO-204 | Site Super | Field Condition | $8,750 | 5d | Pending | 2026-04-27 |
| CO-1043 | Add covered patio extension | SB-305 | Homeowner | Owner Request | $12,300 | 8d | In Review | 2026-04-26 |
| CO-1044 | Foundation redesign - soil | WC-118 | Engineer | Design Error | $15,600 | 12d | Approved | 2026-04-25 |
| CO-1045 | Electrical panel upgrade | PT-007 | Inspector | Code Requirement | $3,400 | 2d | Approved | 2026-04-24 |
| CO-1046 | Window size change | CB-410 | Homeowner | Owner Request | $2,100 | 1d | Pending | 2026-04-23 |
| CO-1047 | Storm drain reroute | BM-203 | Site Super | Field Condition | $9,200 | 6d | In Review | 2026-04-22 |
| CO-1048 | Fireplace addition master BR | AC-509 | Homeowner | Owner Request | $6,800 | 4d | Approved | 2026-04-21 |
| CO-1049 | Retaining wall extension | MR-115 | Engineer | Design Error | $11,400 | 7d | Rejected | 2026-04-20 |
| CO-1050 | Tankless water heater | HO-210 | Homeowner | Owner Request | $1,800 | 1d | Pending | 2026-04-19 |
| CO-1051 | Garage door upgrade insulated | SB-310 | Homeowner | Owner Request | $2,400 | 1d | Approved | 2026-04-18 |
| CO-1052 | Sewer line reroute | WC-122 | Site Super | Field Condition | $13,500 | 9d | Approved | 2026-04-17 |
| CO-1053 | Load bearing wall correction | PT-012 | Engineer | Design Error | $7,600 | 5d | Approved | 2026-04-16 |
| CO-1054 | Fire sprinkler addition | CB-415 | Inspector | Code Requirement | $5,200 | 3d | In Review | 2026-04-15 |
| CO-1055 | Hardwood flooring upgrade | BM-208 | Homeowner | Owner Request | $3,900 | 2d | Pending | 2026-04-14 |